15th February 2017:  RJM International has won an EU competitive tender to upgrade a gas-fired power plant in the Czech Republic to secure full IED compliance.

Located 31kms north-west of Prague, this on-site plant delivers power to a Synthos facility that manufactures rubber and polystyrene products.

The project was started in November 2016 and is scheduled to last for nine months, with commissioning and full operation planned for August / September 2017. The work will be carried out by local sub-contractors, working in partnership with RJM’s specialist engineers.

Commenting on the project win, John Goldring, Managing Director of RJM International, said, “Our award-winning ultra-low NOx Gas CleanAir BurnerTM is ideally suited to this type of retro-fit application, and the innovative technology that is at the heart of our burner means we can help our customers meet their IED limits on primary measures only, in a highly cost-effective manner.

The versatility and effectiveness of our CleanAir BurnerTM technology is well-proven across a number of diverse utility plant references. For example, we have recently completed an ultra-low NOx burner refit on a set of gas-fired boilers at a district heating plant in a suburb of Beijing where we have successfully reduced NOx to an exceptionally low concentration of less than 30mg/Nm3,” he added.

 Synthos site, Kralupy

The Synthos facility at Kralupy in the Czech Republic